By the 1950's Christ Church was nearly a ruin and in danger of
collapsing. The work to repair and restore it has involved consderable
amounts of research and extensive and complex building work.
Summary of Building Works, Research and Investigations since
1978
November 1978 - March 1979
Repair and stabilisation of Sanctuary beam and minor works including
glazing repairs and fitting window guards.
June 1979
Re-opening former South Door.
November 1979
Survey of Tower and Steeple.
November 1979 - 1982
Works to West Portico: stabilisation of structure; strengthening
walls; timber treatment; stone repairs; new leadwork to roof;
new ceilings and rainwater system.
June 1980
Repairs to Nave floors.
May / June1981
Upgrading Electrical Supply: new electrical main, switch gear
and distribution system.
June 1981
Minor works: repairs to windows; provision of window guards and
toilet in South East Vestry.
July 1982 - July 1984
Reinstatement of aisle windows: removal of windows, plasterwork
and stone transoms; rebuilding reveals to openings and forming
new transoms and cills at correct height; installing new iron
window frames in all openings; reglazing and refitting window
guards.
November 1982 - December 1983
Works to West Forecourt: new cast iron railings with stone plinth;
new drains and new paving; resiting the War Memorial; repairs
to the Vault Door and repairs to the pedestals to the columns
of the Portico.
1983 - 1987
Crypt Excavation: setting up excavation including negotiations
with HSE, LBTH and WHO; grant applications to the GLC, Historic
Buildings Division, Nuffield Foundation and the Wellcome Trust;
liaison with the Victoria & Albert Museum and the Natural
History Museum; initial supervision of the excavation; co- ordination
of all building works involved with the excavation; negotiations
concerned with the. "Small Pox" crisis; co-ordination
with the Centre for the Surveillance of Comrnurricable Diseases.
Reinstatement works in the Crypt and Vestry Room on completion
of the excavation.
1986
Advice and Design Proposal for Disabled Lift.
April - July 1987
Restoration of Vestry Room: removal of unsuitable double glazing;
new windows and opening casements; " repairs to the floor
including timber treatment; new electrical services and painting
and decorating.
July - November 1987
Installation of interim Nave heating system.
1987
Minor works including repairs to Nave floor and alterations to
North East Vestry. Parish worship returns.
February - March 1989
Installation of lighting and power circuits in Tower.
1980 - 1990
Report on Aisle Galleries: research into original arrangement
of galleries and organ, including preparation of report on proposed
restoration of galleries and numerous drawings.
December 1991- May 1992
Re-erection of Memorials removed from aisle walls on North West
and South West Gallery staircases.
1997
Consolidation and cleaning of tower and spire.
1999
Cleaning and repair of south façade. Rebuilding of double
flight of Portland stone steps on the south side. Repair of Rectory
yard gate piers and iron gates.
2000
Rebuilding of the timber floor structure of the aisle galleries.
Repair and cleaning of north and east façades. Rebuilding
of the nave parapets.